This article considers the implications of a Party referring a dispute to adjudication concerning a quotation for a compensation event which has been treated as having been accepted, in accordance with the deeming provisions of Core Clause 6 of the NEC3 Form of Contract.

A conundrum that has often arisen upon projects administered under the Engineering and Construction Contract upon which I have been involved concerns where the dividing line falls between the actual Defined Cost of the work already done and the forecast Defined Cost of the work not yet done, particularly when the compensation event is assessed retrospectively by an adjudicator.
Until relatively recently it had been the accepted position that the Notice of Adjudication framed and set the boundaries of any dispute referred to adjudication.